Current research projects

Image Cryogenic liquid piston pumps for cold liquefied gases like LIN, LOX, LHe, LH2, LNG, LAr
Image Practical training, diploma, master, bachelor
Image Low noise and non metallic liquid-helium cryostat
Image Measurement of insulated packaging
Image Software for technical building equipment
Image Thermal engines
Image Helium extraction from natural gas
Image Calibration of Low Temperature Sensors
Image Ice Slurry Generation
Image Performance tests of refrigerant compressors
Image Solar Cooling
Image Low Temperature Measuring Service
Image Certifiable connection types in cryogenics
Image Innovative Parahydrogen Generator Based on Magnets
Image All-in-one device for freeze-drying and production of biomaterial
Image Refrigerants, lubricants and mixtures

You are here:  Home /  Research and Development


Development of test methods and test rigs for stationary integrated refrigeration units

BMWi Euronorm Innokom

02/2017 – 07/2019

Andreas Peusch

+49-351-4081-5221

How efficient is my refrigeration unit?

The objective of the R&D project was the development of a test method for stationary integrated refrigeration units. The test method comprises different device variants, like ceiling mounted, wall mounted or split refrigeration units. The method provides reliable performance data and thus enables a manufacturer-independent efficiency comparison.

Measurements in the 3- or 4-chamber measurement setup were carried out using the calorimeter method with compensation of the ambient conditions. This enabled the measurements of devices with low cooling capacity (0.5 - 4 kW).

In the selected test setup (Figure 1), the cooling capacity is measured indirectly via an electrical power of the compensation heating. To determine the total cooling capacity, the heat input into the calorimeter room and, if necessary, internal loads (sensible and latent heat) have to be added together.

The test method comprises following features:

  • Suitable for low temperature devices (-20 °C) and normal temperature cooling (0 °C)
  • Measurement in the calorimeter room (3- or 4-zone concept)
  • Determination of heat input via enclosure surfaces before power measurement
  • Establishment of equilibrium conditions (settling phase) of the temperatures to be set (up to 24 h)
  • Measuring period up to 6 h with permissible tolerance band of 0.2 K

Conclusion:

  • Results were included in new test standard prEN 17432
  • Establishment of a uniform Europe-wide comparison criterion
  • Performance and efficiency data on a uniform basis leads to higher confidence and thus also to lower consumption costs

Your Request

Further Projects - Research and Development

Image

Multifunctional electronic modules for cryogenic applications

Electronic with less wiring effort - more than 100 sensors via one feedthrough

Image

Certifiable connection types in cryogenics

Detachable and permanent connections, adhesive bond / form closure / force closure

Image

Combined building and system simulation

Scientific analysis of thermodynamic processes in buildings and its systems

Image

Heat2Power

Refining of fuel cell waste heat

Image

Reducing the filling quantity

How much refrigerant must be filled?