Current research projects

Image Development of a Cryogenic Magnetic Air Separation Unit
Image Pulse-Tube-Refrigerator with sealed compressor
Image Innovative Manufacturing Technologies for Cryosorption Systems
Image Hybrid- Fluid for CO2-Sublimation Cycle
Image Laseroptical measurement
Image Testing of mobile leak detectors according to DIN EN 14624
Image Cryostats, Non-Metallic and Metallic
Image Investigation of coolants
Image Verification of storage suitability of cryo tubes
Image Tensile and compression testing
Image Heat2Power
Image Calibration leak for the water bath leak test
Image Humidifier System for High-Purity Gases
Image Investigation according to DIN EN ISO 14903
Image Mass Spectrometer
Image Development of test methods and test rigs for stationary integrated refrigeration units

You are here:  Home /  Research and Development


Development of test methods and test rigs for stationary integrated refrigeration units

BMWi Euronorm Innokom

02/2017 – 07/2019

Andreas Peusch

+49-351-4081-5221

How efficient is my refrigeration unit?

The objective of the R&D project was the development of a test method for stationary integrated refrigeration units. The test method comprises different device variants, like ceiling mounted, wall mounted or split refrigeration units. The method provides reliable performance data and thus enables a manufacturer-independent efficiency comparison.

Measurements in the 3- or 4-chamber measurement setup were carried out using the calorimeter method with compensation of the ambient conditions. This enabled the measurements of devices with low cooling capacity (0.5 - 4 kW).

In the selected test setup (Figure 1), the cooling capacity is measured indirectly via an electrical power of the compensation heating. To determine the total cooling capacity, the heat input into the calorimeter room and, if necessary, internal loads (sensible and latent heat) have to be added together.

The test method comprises following features:

  • Suitable for low temperature devices (-20 °C) and normal temperature cooling (0 °C)
  • Measurement in the calorimeter room (3- or 4-zone concept)
  • Determination of heat input via enclosure surfaces before power measurement
  • Establishment of equilibrium conditions (settling phase) of the temperatures to be set (up to 24 h)
  • Measuring period up to 6 h with permissible tolerance band of 0.2 K

Conclusion:

  • Results were included in new test standard prEN 17432
  • Establishment of a uniform Europe-wide comparison criterion
  • Performance and efficiency data on a uniform basis leads to higher confidence and thus also to lower consumption costs